$REEMF If you're interested in the Bear Lodge Permit process, here's the official Fast 41 link and timeline.
The stated timeline doesn't quite line up with the graph.
Currently slated for a 10/15/27 completion date. Started 04/07/26. That's an 18 month permit. That's longer compared to other permits I've been following; 8-12 months.
They're currently in the Section 106 review. They will be in several sections simultaneously at different stages over the course of the permit.
https://www.permits.performance.gov/permitting-project/fast-41-covered-projects/bear-lodge-rare-earth-project