Oct. 4 at 1:19 PM
$INDO On Oct 2, 2025, <
[email protected]> wrote:
>> I hear you. The frustration you’re expressing is exactly what I’ve been feeling as well. Every day we’re not drilling is a day we’re not producing.
>> To be fully transparent: in August, SKK Migas issued updates to PTK-007 (the procurement guideline). Those changes required us to re-do vendor pre-qualification and documentation for drilling services (CIVD, supporting letters, and internal approvals), which has pushed our Kruh timeline again. You may search on google regarding this matter
>> That said, I completely agree we must pivot while the Kruh paperwork catches up:
>> • We are progressing parallel work so Citarum can move once long-lead items and approvals line up.We’re also advancing new projects where we already have MOUs, and—frankly—evaluating other geographies with more competitive concession terms to avoid this kind of regulatory drag going forward.
>> I am as speechless and angry with this process as you are